How do you install restaurant kitchen exhaust ducts? Clear exhaust decides whether a kitchen can work safely. CHINENG shares installation basics.

Installation methods
1. Do not bury demountable duct joints in walls or floor slabs.
2. Embed hangers accurately and securely; keep embedded parts unpainted and clean. Unless designed otherwise:
1) Horizontal: spacing 4 m if diameter/long side <400 mm; 3 m if ≥400 mm.
2) Vertical: spacing 4 m with ≥2 fixings per riser.
3) Insulated ducts follow design.
4) No hangers at outlets, valves, or access doors; do not hang on flanges; add sway braces.
5) Fire dampers and motorized dampers need dedicated supports.
6) Flange gaskets 3–5 mm thick, not protruding inside; nuts on one side.
7) Horizontal levelness ≤3/1000 (total ≤20 mm); vertical plumb ≤2/1000 (total ≤20 mm).
8) Place damper operators for access; blades insert with airflow; install fusible links after system install.
9) Diffusers square, accurate, free-moving, firmly connected.
10) Flexible connectors neither too tight nor twisted.
3–6. Fabrication allowances cover fittings and hangers (not floor stands); flexible ducts may be metal or polymer films; guide vanes share one item; taper-duct uniform-supply systems use average size with labor ×2.5.
Exhaust design tips
1. Keep horizontal runs short—usually ≤15 m with ~2% slope and a cleanout at the end.
2. Duct velocity preferably ≥10 m/s so grease does not settle.
3. Branch dampers at hood connections; main duct about 8–10 m/s; hood throat about 4–5 m/s.
Follow the CHINENG website for more kitchen engineering and equipment solutions.
Price transparency
Nationwide coverage
Rapid design
Quick quote
Worry-free after sale
Guangdong Jiushang Electronic Technology Co., Ltd.
+86-400-0622-168
Mobile: +86-135-2862-7820
Contact: Manager Liu
Address: Building 5, Huyue Bay Area, Humen Town, Dongguan City, Guangdong Province, China